Projects

0
Projects

Number of completed projects

ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Design and Supply the Equipment for 66/20 KV Conventional SubstationsSyriaPEDEEEEPC2000FinishedPrime ContractorPower T&D
2Construction of 20 KV Compact SubstationSyriaPEDEEEEPC2000FinishedPrime ContractorPower T&D
3Construction of Jableh (230/66/20) KV SubstationSyriaPEEGTEPC2001FinishedPrime ContractorPower T&D
4Construction of the Al Sinn 66/6.3 KV SubstationSyriaMinistry of IrrigationEPC2001FinishedPrime ContractorPower T&D
5Construction of the Ain-Albaida 66/6.3 KV SubstationSyriaMinistry of Irrigation – Coastal BasinEPC2001FinishedPrime ContractorPower T&D
6Design, Supply, and Erection of the Equipment Al-Bab Tadef Irrigation ProjectSyriaGOLDEPC2002FinishedPrime ContractorWater & Sewage

 

ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Development of Agarak and shinuhair Substation and Second Power Transmission Lines of 220 kVArmeniaHVENEPC2000FinishedPrime Contractor Power T&D
2Complementary Contract for Supply, Construction, Erection, and Commissioning of Agarak 220 KV Substation  ArmeniaArmenergoEPC2000FinishedPrime Contractor Power T&D
3Construction of 220/110 KV Overhead Lines and Related Substations ArmeniaHVENEPC2000FinishedPrime Contractor Power T&D
4Engineering, Procurement, Installation, and commissioning of the wind farm in Pushkin-PassArmeniaHVENEPC2003FinishedPrime Contractor Power Generation
5EPC Construction of Iran-Armenia 400KV Third Power Transmission Line and Related SubstationArmeniaHVENEPC2015ActivePrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Design, Supply, Erection, Commissioning and Consultation for Operation of 2 Mobile Substations LebanonEDLEPC2001FinishedPrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Reconstruction and Utilization of Karakalpakstan Zone Subterranean Waters UzbekistanUzbekenergoEPC2002FinishedPrime Contractor Water & Sewage
2EPC Construction of Bukhara Water Treatment PlantUzbekistan SUE «Suvokova» of Bukhara RegionEPC2017ActivePrime Contractor Water & Sewage
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Construction of  Overhead Transmission Lines and Substations AzerbaijanAzerenerjiEPC2003FinishedPrime Contractor Power T&D
2Construction of 330 and 220 KV Overhead Transmission Lines and Substations AzerbaijanAzerenrji JSC EPC2005FinishedPrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Implementation of 225 KV Transmission Line and 225/132 KV Substation IraqMinistry of Electricity of IraqEPC2004FinishedPrime Contractor Power T&D
2EPC of 2×160 MWt Gas Turbine Al-Sadir PowerplantIraqPower MinistryEPC2007FinishedPrime Contractor Power Generation
3Installation and Commissioning of 2*160MW DIBIS GAS TURBINE POWER PLANT KirkukIraqMinistry of Electricity of IraqEPC2011ActivePrime Contractor Power Generation
4Operation and Maintenance of Al-Sadir gas Turbine Power Plant for 6 monthsIraqMinistry of Electricity of IraqEPC2012FinishedPrime Contractor Power Generation
5Operation and Maintenance of Al-Sadir gas Turbine Power Plant for 6 monthsIraqMinistry of Electricity of IraqEPC2013FinishedPrime Contractor Power Generation
6EPC Construction of 12 MW STEAM TURBINE power plant- Al EmarahIraqMinistry of Industry and mineral states EPC2014ActivePrime Contractor Power Generation
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Construction of 225KV Touba – Tobene – Kaolack Transmission Lines and SubstationsSenegalSenelecEPC2005FinishedPrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Design, Supply, and Supervision of Banes Water Treatment PlantCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
2Design, Supply, and Supervision of Guanta Water Treatment PlantCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
3Supply the Equipment for Camaguey Water Treatment PlantCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
4Supply the Equipment for Las Tunas Water Treatment PlantCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
5Design, Supply, and Supervision of Jesus Menendez Water Treatment PlantCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
6Design, Supply, and Supervision of Compact Water Treatment PlantsCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
7Design, Supply, and Supervision of La Maya Water Treatment PlantCubaCuba HidraulicaEPC2005FinishedPrime Contractor Water & Sewage
8Design, Supply, and Supervision of Palma Soriano Water Treatment PlantCubaCuba Hidraulica EPC2005FinishedPrime Contractor Water & Sewage
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1EPC Construction of Dadu-Khuzdar 220KV Double Circuit Transmission Line PakistanNTDCEPC2008FinishedLeader of JVPower T&D
2EPC Construction of Dadu-Khuzdar 220/132 Kv Substation PakistanNTDCEPC2008FinishedLeader of JVPower T&D
3EPC Construction of Gwader 220KV Transmission LinePakistanNTDCEPC2012ActivePrime Contractor Power T&D
4EPC Construction of Gwader 220/132kV GIS SubstationPakistanNTDCEPC2013ActivePrime Contractor Power T&D
5500 kv D/C Two T/Lines for Looping In & Out of 500 kv Dadu- Guddi Transmission line Circuits 1 & 2 and 220kv D/C  T/Line for looping in & out of 220 kv Guddu- Sibbi T/Line at 500 kv Shikarpure Substation. PakistanNTDCEPC2013FinishedLeader of JVPower T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Extension of 230 kV Substations (Interconnection to Sudan)EthiopiaEEPCOEPC2009FinishedPrime Contractor Power T&D
2EPC Construction of 230/33/15kV Wolkayit Sugar Factory SubstationEthiopiaEthiopian Electric Power (EEP)EPC2014ActivePrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Water supply system at Niabd Jabal Akhtar in Welayat of NizwaOmanPAW (public authority of Electricy and water)EPC2009FinishedPrime Contractor Water & Sewage
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Rural Electrification ProjectSrilankaCeylone Electricity BoardEPC2011FinishedPrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Supply of 110/20 kV Substation and Transmission line from Rabat Kashan (Turkmenistan) to Kale-e-Naw City (Afghanistan)AfghanistanMinistry of Energy and WaterEPC2012ActivePrime Contractor Power T&D
2Execution of 20Kv OverHead Tranmission Line From Neribabad Substation to Gorimar Industrial Park Mazar-e-Sharif Afghanistan Afghanistan Investment Support Agency (AISA)EPC2012FinishedPrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1EPC constrcution of 4 Mobile Substation 132/33/11 kV Kurdistan Regional GovernorateMinistry of Electricity of IraqEPC2013FinishedPrime Contractor Power T&D
2EPC constrcution of 3 Mobile Substation 132/33kV & 3 mobile substation of 33/11kVKurdistan Regional GovernorateMinistry of Electricity of IraqEPC2014ActivePrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1Engineering and Procurement of 110/6.3 KV Garry-Kariz SubstationTurkmenistanMinistry of EnergyEPC2013FinishedPrime Contractor Power T&D
ItemSubjectCountryClientTypeStartring YearStatusRole of SunirSector
1220/33 kV Substation at Mtera Hydropower PlantTanzainaRural Energy AgencyEPC2017ActivePrime Contractor Power T&D
0
Procurement

Number of Procurement

1Supply 23 Diesel GeneratorsTurkmenistanMinistry of Agriculture P1996FinishedPrime Contractor 
2Purchase of Electricity TurkmenistanTurkmenenergoP2002FinishedPrime Contractor 
3Supply and Commissioning of PLC EquipmentTurkmenistanTurkmenenergoP2002FinishedPrime Contractor 
4Purchase of Electricity TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
5Supply of Compact Energy Equipment and Digital Measurement System TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
6Supply Current TransformersTurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
7Supply Rechargeable Batteries TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
8Supply PVC Sheathing CompoundTurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
9Supply Paper for Compact Energy Project TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
10Supply Gas Insulated Circuit Breakers TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
11Supply Air Cables TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
12Supply Disconnecting Switches TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
13Supply Electro MotorsTurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
14Delivery of Electrical Energy from Turkmenistan to IranTurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
15Delivery of Electrical Energy from Turkmenistan to IranTurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
16Delivery of Electrical Energy  from Turkmenistan to IranTurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
17Supply Caustic Soda TurkmenistanTurkmenenergoP2003FinishedPrime Contractor 
18Supply Phase Disconnector Switches TurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
19Supply Diesel GeneratorsTurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
20Supply Substation Equipments (PLC) TurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
21Supply Cable Head and ConnectorsTurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
22Purchase Copper Plates TurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
23Supply Transformer for Substation TurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
24Supply Digital Energy MeterTurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
25Supply Voltage Transformer TurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
26Supply  Filtering Elements and Carbon BrushTurkmenistanTurkmenenergoP2004FinishedPrime Contractor 
27Supply MV Cables   TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
28Supply Console Street Light and Sodium Arc LampTurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
29Supply One-Stage Nozzle TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
30Supply Line Feeder Protection Panel TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
31Supply ConnectorsTurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
32Supply LV EquipmentTurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
33Supply Connectors TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
Supply Joints for Polymeric Armoured Cables TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
34Supply Current and Voltage TransformersTurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
Supply Current Transformers TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
 Irrigation Project in The City of AshgabatTurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
 Supply Personal Computers and Printers TurkmenistanTurkmenenergoP2005FinishedPrime Contractor 
Supply 36 KV Switchgear TurkmenistanTurkmenenergoP2006FinishedPrime Contractor 
35Supply Circuit BreakerTurkmenistanTurkmenenergoP2006FinishedPrime Contractor 
Supply Protection Panel TurkmenistanTurkmenenergoP2006FinishedPrime Contractor 
Supply Surge Arrester TurkmenistanTurkmenenergoP2006FinishedPrime Contractor 
Supply Circuit BreakersTurkmenistanTurkmenenergoP2006FinishedPrime Contractor 
36Supply Cylindrical Cartridge Filtering Element TurkmenistanTurkmenenergoP2006FinishedPrime Contractor 
MV Cable, 10kV, 3×150TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
MV Cable, 10kV, 3×185TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
37MV Cable, 10kV, 3×240TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
Digital protection panel GE with relay D60+F60.control circuit 110VDC of TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
Digital protection panel GE with relay D60+D60.control circuit 110VDC of TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
AC Iном = 1A  & Uном =100VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
38Marshaling kiosk for control cablesTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
Cable plasticate PVC-granules  GPS 8450 N: Insulating white colorTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
Cable plasticate PVC – granules  GPS 8450: TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
Black  colorTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
39Current transformer 245 kV with 4 cores:TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1000-2000/1 class 0,5FS 30VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1000-2000/1 class 5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1000-2000/1 class 5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1000-2000/1 class 5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
40Current transformer 110 kV with 4 cores:TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
100-200-400/5 class  0,5FS5 30VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
100-200-400/5 class  5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
100-200-400/5 class 5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
Current transformer 35 kV with 2 cores:TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
41300-600/5 class  0,5FS5 30VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
42300-600/5 class  5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
43Current transformer 35 kV with 3 cores:TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
44300-600/5 class  0,5FS5 30VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
45300-600/5 class  5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
46300-600/5 class  5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
47Current transformer 35 kV with 3 cores:TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
48500-1000/5 class  0,5FS5 30VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
49500-1000/5 class  5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
50500-1000/5 class  5P20 60VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
51Voltage transformer 110kV, transformationTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
52Ratio 110000/ 100/ 100VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
53          Ö3        Ö3 TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
54Core class a-n 0,5/3P 100VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
55Core class  da-dn 3P 100VA   TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
56Voltage transformer 35kV, transformationTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
57Ratio 35000/ 100/ 100VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
58         Ö3        Ö3 TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
59 Core class a-n 0,5/3P 100VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
60 Core class  da-dn 3P 100VATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
61Throttle (ballast) for street lamps 125 VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
62Throttle (ballast) for street lamps 250 VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
63Throttle (ballast) for street lamps 400 VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
64Sensor control (vibrograph) for testing CB -145kV (LTB-145)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
65Sensor control (vibrograph) for testing CB -245kV TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
66Sensor control (vibrograph) for testing HPL  -245/31BTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
67Sensor clamp mechanism of CB – 145kV (LTB-145)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
68Sensor clamp mechanism of CB – 245kV (HPL-245/31 B1)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
69Manual computer (Laptop) with program for removing speed characteristic curve of CB-145,245 kVTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
70SF6 leak detector type CPS refrigant Leak-Seeker production of  USATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
71Compressor for SF6 injection type DILO production of Germany (without gas injection compressor)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
72GUSJ-42/120-240-3HL (SMOE-62789) TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
73GUSJ-12/70-120 (SMOE-61811)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
74GUSJ-12/150-240(SMOE-61812)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
75GUST-12/70-120/800-L12(SMOE-61789-L12)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
76GUST-12/150-240/800-L12(SMOE-61790-L12)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
77GUSJ-01/4X50-150(SMOE-81652)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
78GUSJ-01/4X120-240(SMOE-81653)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
79ERKT-36D1MO-CEE01TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
80EAKT-1678TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
81EAKT-1679TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
82POLJ-12/3X120-240-TTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
83POLT-12D/3XOH4-L12ATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
84POLT-12D/3XO-H4-L12BTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
85POLJ-12/3X70-150-ТTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
86Single phase DS Pantograph without earthing blades, 245kV, 1250A, Isc=31,5кАTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
87Protection Panel of automatics & control of 3winding Tr, type RP-B01 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
88Protection Panel of automatics & control of 3 winding Tr, type RP-B02 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
89Protection Panel of automatics & control of   Tr bushings 35kV, type RP-C01 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
90Protection Panel of automatics & control of  OHL 35kV   (on the one panel for two lines), type RP-C02 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
91Protection Panel of automatics & control of MCB 35kV   & TH -35k, type RP-C04 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
92Protection Panel of automatics &  control of double-winding Tr, type RP-B001 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
93Protection Panel of automatics & control of double-winding Tr, type RP-B002 control circuit 220VDCTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
94AC panel with change over with ABP 0,4 kV type AC-P, 50kA, 380/220V, 50HZTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
95DC panel with distribution of automatics & insulation control, type DC-PTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
96Control panel for 2 connections ( on 1 panel), Panel maintains CB & DS & interlock, synchronization circuit, warning circuit, CT control circuit TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
97Console Street Light 250W with Sodium Arc LampTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
98Console Street Light 400W with Sodium Arc LampTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
99Sodium Arc Lamp 250WTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
100Sodium Arc Lamp 400W  TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
101Throttle (ballast) for street lamps 110VTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
102MV Cable, 10kV, 3×150TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
103MV Cable, 10kV, 3×185TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
104GUSJ-42/120-240-3HL (SMOE-62789) TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
105GUSJ-12/150-240(SMOE-61812)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
106GUST-12/70-120/800-L12 (SMOE-61789-L12)TurkmenistanEnergoenjamP2007FinishedPrime Contractor 
107POLJ-12/3X70-150-ТTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
108CB145kV LTB145D1/BTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1093 phase DS with earthing blade 110kV type NSA 145/1250 C DS+ESTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1103 phase DS with earthing blade 110kV type NSA 145/1250 C DS+2ESTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1113 phase DS without earthing blade 110kV type NSA 145/1250 C DSTurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1123 phase DS with 1 set of earthing blade 245kV, 1250A, Isc=31.5kATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1133 phase DS with 2 set of earthing blade 245kV, 1250A, Isc=31.5kATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
114Earthing switch of neutral point of power Tr.(single phase earthing blade 110kV, 1250ATurkmenistanEnergoenjamP2007FinishedPrime Contractor 
1Supply Complete Set of MV and LV WindingsSyriaPEDEEEP1997FinishedPrime Contractor 
2Supply Single Phase WH-Meters SyriaPEDEEEP1997FinishedPrime Contractor 
3Supply 100 KVA TransformersSyriaPEDEEEP1997FinishedPrime Contractor 
4Consultation on Electricity Distribution SyriaPEDEEEP1997FinishedPrime Contractor 
5Dispatch Two Iranian Power Experts to Syria SyriaPEDEEEP1997FinishedPrime Contractor 
6Supply 16 KVA Circuit Breakers  SyriaPEDEEEP1997FinishedPrime Contractor 
7Supply 630 KVA Transformers SyriaPEDEEEP1997FinishedPrime Contractor 
8Supply 630 KVA  Transformers SyriaPEDEEEP1997FinishedPrime Contractor 
9Supply 630 KVA TransformersSyriaPEDEEEP1997FinishedPrime Contractor 
10Supply Single Phase WH-MetersSyriaPEDEEEP1998FinishedPrime Contractor 
11Supply 100 KVA TransformersSyriaPEDEEEP1998FinishedPrime Contractor 
12Supply 400 KVA Transformers  SyriaPEDEEEP1998FinishedPrime Contractor 
13Supply 400 KVA Transformers  SyriaPEDEEEP1998FinishedPrime Contractor 
14Supply Cast Ductile Pipes and ConnectionsSyriaPEWSSAP1998FinishedPrime Contractor 
15Supply 400 KVA Distribution TransformersSyriaPEDEEEP1998FinishedPrime Contractor 
16Supply Single Phase WH-MetersSyriaPEDEEEP1998FinishedPrime Contractor 
17Supply 100 KVA Oil Immersed Distribution TransformersSyriaAPCDP1998FinishedPrime Contractor 
18Supply Ductile PipesSyriaPEWSSAP1998FinishedPrime Contractor 
19Repair and Maintenance Power Transformers SyriaPEDEEEP1999FinishedPrime Contractor 
20Supply of Steel Towers 66 KV OHTL SyriaPEDEEEP1999FinishedPrime Contractor 
21Repair and Maintenance of Transformers SyriaPEEGTP1999FinishedPrime Contractor 
22Supply 400 KVA Distribution TransformersSyriaPEDEEEP1999FinishedPrime Contractor 
23Supply Caustic SodaSyriaGeneral Company of Homs RefineryP1999FinishedPrime Contractor 
24Supply Distribution Transformers SyriaSPCP2000FinishedPrime Contractor 
25Supply 200 KVA TransformersSyriaGECOLP2000FinishedPrime Contractor 
26Supply Steel Towers for 66 KV OHTLSyriaPEDEEEP2000FinishedPrime Contractor 
27Supply Porcelain Line InsulatorsSyriaPEDEEEP2000FinishedPrime Contractor 
28Supply 30 MVA Power TransformersSyriaPEDEEEP2000FinishedPrime Contractor 
29Dispatch Iranian Power Experts to Syria SyriaPEEGTP2000FinishedPrime Contractor 
30Supply 100 KVA Distribution TransformersSyriaPEDEEEP2000FinishedPrime Contractor 
31Study and Modernize an Irrigation ProjectSyriaMinistry Of  Irrigation P2000FinishedPrime Contractor 
32Supply the Equipment for Jarid Al Enazza Water ProjectSyriaMHUP2000FinishedPrime Contractor 
33Supply Joint Sealant SyriaRIMAP2000FinishedPrime Contractor 
34Repair Spare Parts of Power Stations SyriaPEEGETP2001FinishedPrime Contractor 
35Supply 100 KVA Electrical TransformersSyriaSyrian Arab Republic Telecommunication EstablishmentP2001FinishedPrime Contractor 
36Supply 100 KVA Eelectrical TransformersSyriaSyrian Arab Republic Telecommunication EstablishmentP2001FinishedPrime Contractor 
37Supply 200 KVA Distribution TransformersSyriaPEDEEEP2001FinishedPrime Contractor 
38Supply Steel Towers for Overhead TLSyriaPEDEEEP2001FinishedPrime Contractor 
39Supply 400 KVA Distribution TransformersSyriaPEDEEEP2001FinishedPrime Contractor 
40Supply 1600 and 200 KVA Distribution Transformers SyriaSyrian Modern CableP2001FinishedPrime Contractor 
41Supply 200 KVA Distribution TransformersSyriaPEDEEEP2001FinishedPrime Contractor 
42Supply Single Phase WH-Meter Spare PartsSyriaPEDEEEP2001FinishedPrime Contractor 
43Supply Single Phase WH-MetersSyriaPEDEEEP2001FinishedPrime Contractor 
44Supply Single Phase WH-MetersSyriaPEDEEEP2001FinishedPrime Contractor 
45Supply the Equipment for Chlorine CenterSyriaPEWSSAP2001FinishedPrime Contractor 
46Supply Caustic SodaSyriaGeneral Company of Homs RefineryP2001FinishedPrime Contractor 
47Feasibility Study of Kattine Lake ProjectSyriaMinistry of IrrigationP2001FinishedPrime Contractor 
48Supply Faucets SyriaRIMAP2001FinishedPrime Contractor 
49Regulating the flow of the Northern Kebir RiverSyriaMOI P2001FinishedPrime Contractor 
50Provide Consultation ServicesSyriaPEDEEEP2002FinishedPrime Contractor 
51Repair Transformer SyriaGeneral FERTILIZER CoP2002FinishedPrime Contractor 
52Supply & Installation of One Unit SubstationSyriaJoud Steel Co.P2002FinishedPrime Contractor 
53Study Social and Environmental Effects of Modernizing and Irrigation ProjectSyriaMinistry of IrrigationP2002FinishedPrime Contractor 
54Study Water Reservoir ProjectSyriaMOIP2002FinishedPrime Contractor 
55Supply Distribution TransformersSyriaSPCP2003FinishedPrime Contractor 
56Supply 20 KV CellsSyriaPEDEEEP2004FinishedPrime Contractor 
57Provide Training for Engineers at PEDEEESyriaPEDEEEP2004FinishedPrime Contractor 
58  Repair TransformerSyriaPEEGTP2005FinishedPrime Contractor 
59Supply 66 KV Current and Voltage TransformersSyriaPEDEEEP2005FinishedPrime Contractor 
60supply of 300MVA-400/230/20 kv power transformers, quantity /4/SyriaPETEP2014ActivePrime Contractor 
61supply of 125MVA-230/66 kv power transformers, quantity /6/SyriaPETEP2014ActivePrime Contractor 
62supply of 30MVA-66/20 kv power transformers, quantity /50/SyriaPETEP2014ActivePrime Contractor 
63 supply of external equipments for substations (Circuit Breaker Qty /80/, Disconnecting Switch Qty /200/, Current Transformer Qty /70/, Voltage Transformer Qty /70/SyriaPETEP2014ActivePrime Contractor 
64supply of Low Voltage Circuit Breakers (100-200-400-800-1250-2000-2500) Amp and tests attendance SyriaPEDEP2014ActivePrime Contractor 
65supply of 200 KVA-20/0.4 kv distribution transformers, quantity /1000/, with spare parts and attending tests.SyriaPEDEP2014ActivePrime Contractor 
66supply of 400 KVA-20/0.4 kv distribution transformers, quantity /522/, with spare parts and attending tests.SyriaPEDEP2014ActivePrime Contractor 
67supply of 400 K.v (/78/ Current transformers,/30/ Capacitive voltag, /12/ Surge Arrestor complete with surge counter) SyriaPETEP2014ActivePrime Contractor 
68supply of Package Substation (630-1000)  KVA,  quantity /400/, with spare parts, attending tests and internal trainingSyriaPEDEP2014ActivePrime Contractor 
1Supply 33 KV Line Post Insulators Saudi Arabia SCECO-CP1999FinishedPrime Contractor 
2Supply 33 KV Line Post Insulators Saudi Arabia SCECO-CP1999FinishedPrime Contractor 
3Supply 15 KV Open Fuse Cut Outs Saudi Arabia SCECO-CP1999FinishedPrime Contractor 
4Supply 15-27 KV Fuse Cut OutsSaudi Arabia Al-Babtain Co. P2000FinishedPrime Contractor 
5Supply LV Current TransformersSaudi Arabia SECO-CP2000FinishedPrime Contractor 
6Supply 33 KV Cut Out Fuses Saudi Arabia SECOP2000FinishedPrime Contractor 
7Supply Current Transformers Saudi Arabia SECO-CP2001FinishedPrime Contractor 
8Supply Current Transformers Saudi Arabia SECO-CP2001FinishedPrime Contractor 
9Supply 100 Amp Open Fuse Cut OutsSaudi Arabia SECO-CP2001FinishedPrime Contractor 
10Supply Capacitor Bank Saudi Arabia Abdullah N. El-Mosa EST. P2001FinishedPrime Contractor 
11Supply 33.1 KV, 1000 KVA Distribution TransformerSaudi Arabia Abdullah N. El-Mosa EST. P2001FinishedPrime Contractor 

 

1Supply Copper Power Cable ArmeniaSevan-Razda Kaskad P1998FinishedPrime Contractor 
2Supply Lead acid Batteries ArmeniaVorotan Power Station Kaskad-Goris P1999FinishedPrime Contractor 
3Supply, Construction, Erection, and Commissioning of Agarak 220 KV Substation ArmeniaArmenergoP2000Finished Prime Contractor 
4Rehabilitation of Aparan and Khalavar DamsArmeniaMinistry of AgricultureP2000FinishedPrime Contractor 

 

1Provide Consultation on Electricity DistributionYemenMinistry of Electricity and WaterP1998FinishedPrime Contractor 
2Supply Transformers YemenPublic Electricity CorporationP1998FinishedPrime Contractor 
3Supply ACSR ConductorsYemenPublic Electricity Corporation P1998FinishedPrime Contractor 
4Supply Distribution TransformersYemenMarubani Construction Machinery Europe S.A. P2000FinishedPrime Contractor 
5Supply ACSR ConductorYemenMarubani Construction Machinery Europe S.A. P2000FinishedPrime Contractor 
6Supply Arrival Cables YemenPublic Telecommunication CorporationP2000FinishedPrime Contractor 
7Supply Distribution TransformersYemenPTCP2002FinishedPrime Contractor 
8Supply Distribution TransformersYemenPTCP2002FinishedPrime Contractor 

 

1Supply 33 KV Cut Out FusesJordanIDECOP1999FinishedPrime Contractor 
2Supply 11 KV Cut Out FusesJordanJEPCO P1999Finished Prime Contractor 
3Supply 33 KV Post Insulators Jordan EDCOP1999FinishedPrime Contractor 
4Supply Cap and Pin Tension Isolator Discs Jordan JEPCOP1999FinishedPrime Contractor 

 

1Supply Distribution Transformers LibyaGECOLP1995FinishedPrime Contractor 
2Supply MV/LV Cable (PVC/XLPE) LibyaGECOLP1995FinishedPrime Contractor 
3Supply Single/Three-Phase WH-Meter LibyaGECOLP1995FinishedPrime Contractor 
4Supply Distribution Transformers LibyaNobel Trading P2001FinishedPrime Contractor 

 

1Supply Single Phase WH-Meters LebanonEDLP2001FinishedPrime Contractor 
2Supply Cut Out Fuses LebanonBab International P2001FinishedPrime Contractor 
3Supply Single Phase WH-MetersLebanonEDLP2002FinishedPrime Contractor 
4Supply of HV Equipment (Surge Arrester & Transformers)LebanonEDLP2009FinishedPrime Contractor 

 

1Supply LV and MV Capacitor BanksIraqMinistry of  Electricity of IraqP2004FinishedPrime Contractor 
2Export electrical energy to IraqIraqMinistry of  Electricity P2004FinishedPrime Contractor 
3Supply of 400 & 132kV Toughened Glass InsulatorsIraqMinistry of ElectricityP2015ActivePrime Contractor 

 

1Supply 30 Tons of  ACSR Conductors AzerbaijanAzekonP2003FinishedPrime Contractor 

 

1Supply the equipment for Havana Water Treatment PlantCubaCuba Hidraulica P2005FinishedPrime Contractor 
2Supply the Equipment for Holguin Water Treatment PlantCubaCuba Hidraulica P2005FinishedPrime Contractor 

 

1Supply 100 KVA Transformers PakistanWAPDAP2002FinishedPrime Contractor 
2Supply of Panels and Termination Kits PakistanWAPDAP2002FinishedPrime Contractor 

 

1Supply of three phase meter AfghanistanDABSP2015ActivePrime Contractor 

 

Read More
Al-Bab Tadef Design, Supply, and Erection of the Equipment Irrigation Project

Al-Bab Tadef Design, Supply, and Erection of the Equipment Irrigation Project

Read More
Cuba 10 Projects: Water Treatment Plant and Pumping Station

Cuba 10 Projects: Water Treatment Plant and Pumping Station

Read More
Kurdistan Region 3 x 132/11 & 3 x 132/11 Mobile Substations

Kurdistan Region 3 x 132/11 & 3 x 132/11 Mobile Substations

Read More
Kurdistan Region 4 Mobile Substations 132/11 KV

Kurdistan Region 4 Mobile Substations 132/11 KV

Read More
AFGHANISTAN / Mazarsharif 20 KV Transmission Line

AFGHANISTAN / Mazarsharif 20 KV Transmission Line