Following negotiations between Sunir Company and the project manager of Iraq’s Dibis Power Plant, until a new contract is reached, Sunir Company has carried out the following work in recent days in order to expedite the implementation and completion of the project:
Adjusting and leveling concrete bed of sewage manholes and, adjusting and leveling the bed of compressed air line slippers, modification of temporary perimeter fences as well as bending and cutting of reinforcement steel bars for concrete , reinforcement and molding of airline slipper foundations, were the most important works that have been implemented recently.
It is clear that this executive policy, which has been adopted due to the limitations of manpower, budget and cash flow of contractors, difficulty of obtaining visas, non-payment of status and problems related to the outbreak of coronavirus, after agreeing with the employer on the minimum requirements for the project will be changed so that Sunir can fulfill its contractual obligations.