According to the public relations report of Sunir Company, a meeting was held on Tuesday, 11th of May, 2021 in the form of a video conference between Mansur Saeedi, CEO of Sunir Company, and Hayek Haroutonian, CEO of HVEN Armenia.
At the beginning, Saeedi give the report about latest activities carried out in the project, the progress of the work and the groups stationed on the site, and added that there are currently a total of 191 people in the transmission line section and in the construction fronts of road construction, drilling, concreting, tower installation, and the wiring is working. At the same time, 62 people are working in the construction operations department at Noravan substation, and the installation team will be sent to the site this week.
In the end, the CEO of HVEN Company expressed her relative satisfaction with the situation of the site and it was decided that HVEN Company will accelerate the opening of work fronts in all 6 parts of project.